The history of Maine’s only commercial nuclear generating station—from construction and operation to closure, dismantling, and its lasting local impact.

The Maine Yankee Atomic Power plant was built between 1968 and 1972 at a reported cost of $231 million in Wiscasset. The site offered access to fresh and salt water, rail and highway connections, nearby electrical demand and transmission lines, and bedrock suitable for foundations.

Power and local prosperity

During its operating life, the plant was Maine’s largest generator of electricity. It produced approximately 119 billion kilowatt-hours for Maine and the wider New England power system.

The facility also transformed municipal finances. Its property-tax payments supported local services and helped fund improvements to schools, parks, roads, public safety, a community center, and ambulance service. Its workforce of roughly 480 full-time employees contributed additional spending to the local economy.

Debate, shutdown, and closure

Maine Yankee operated from 1972 to 1996. It remained open after three statewide citizen-initiated ballot measures in 1980, 1987, and 1992 sought to close it.

The plant shut down in 1995 after cracks were found in steam-generator tubes. It did not return to sustained operation. In August 1997, the company chose permanent closure and decommissioning.

Dismantling the station

Major dismantling continued into the next decade. In 2004, remaining structures were demolished and material was transported to disposal facilities outside Maine. The reactor pressure vessel traveled by barge to a low-level radioactive-waste facility in Barnwell, South Carolina. The reported decommissioning cost was approximately $568 million.

Spent nuclear fuel remained in secure interim storage at the former plant site after decommissioning. This distinction is important: dismantling a generating station does not by itself resolve the long-term disposition of its spent fuel.

Economic aftermath

Closure removed a major source of tax revenue and employment from Wiscasset. The town consequently faced budget reductions and higher taxes while adjusting its services and finances to the loss of the plant.

The Maine Yankee story connects energy production, industrial regulation, local government, employment, environmental management, and the long obligations that follow a nuclear facility’s operating life.

Chronology

From construction to decommissioning

Four periods frame the plant’s place in Maine’s industrial and community history.

Construction begins

Work starts on the nuclear generating station at Wiscasset.

Commercial operation

The station enters service and becomes a major regional electricity source.

Permanent closure

Following operating problems, the decision is made to dismantle the facility.

Major demolition

Remaining plant structures are demolished and material is removed.

Electrical transmission towers beneath an open sky
Why this entry matters

One facility, several connected histories

Maine Yankee was more than a power station. Its operation influenced electricity supply, industrial employment, municipal taxes, public services, statewide ballot debates, and environmental oversight.

Its closure also illustrates how the effects of a large industrial facility continue after electricity production ends. Decommissioning, waste management, lost employment, and municipal adjustment became part of the plant’s longer legacy.

Additional resources

Sources noted for this entry

Books, reports, studies, and archival collections provide routes into the policy, economic, and decommissioning record.

Legacy for Our Children

H. G. Brack, ed. A 1993 study of decommissioning costs and legislative policy questions.

The Effects of a Mandatory Early Shutdown

Maine State Planning Office, 1987. An examination of the economic implications of early closure.

Maine Yankee site and waste studies

Company histories and state materials document operation, decommissioning, and spent-fuel storage.

Archival collections

The University of Maine’s Raymond H. Fogler Library Special Collections holds documents and studies related to the plant.

Utopias: A Brief History

Howard P. Segal, Wiley-Blackwell, 2012.

“Remember the Maine Yankee”

Colin Woodard, Bulletin of the Atomic Scientists, volume 57, issue 1, 2001.

FAQ

Understanding Maine Yankee

Concise answers to common questions about the plant and its legacy.

Where was Maine Yankee located?

The station was in Wiscasset, where access to water, transportation, transmission lines, and suitable bedrock influenced the site choice.

When did the plant operate?

It entered operation in 1972 and last generated electricity in 1996.

Why did Maine Yankee close?

The plant shut down after cracks were identified in steam-generator tubes. It did not return to sustained operation, and permanent closure was chosen in 1997.

Did Maine voters consider closing the plant?

Yes. Statewide ballot measures seeking closure appeared in 1980, 1987, and 1992. The plant remained open after each vote.

How did the plant affect Wiscasset?

It provided jobs and substantial tax revenue that supported public services and infrastructure. Closure required the town to adjust to lower revenue and reduced local employment.

What happened during decommissioning?

Plant systems and structures were dismantled, material was transported to disposal facilities, and the reactor pressure vessel was shipped to South Carolina.

What happened to the spent nuclear fuel?

Spent fuel remained in secure interim storage at the former plant site after the generating station was dismantled.

↑ Top