Passamaquoddy Tidal Power Project

A sweeping proposal to harness the tides of Passamaquoddy and Cobscook bays—and the economic, political, and environmental obstacles that kept it from being built.

The Passamaquoddy tidal power proposal was among Maine’s most ambitious twentieth-century infrastructure ideas. It sought to use the exceptional tidal range along the eastern border to generate electricity, but it never secured the durable financial, political, and cross-border support required for construction.

“Quoddy is an example of a project planned by private capital and supported by pressure groups, but which could not be financed without public aid.”

That was Lincoln Smith’s assessment of the long-studied but unfunded hydroelectric scheme in Washington County. Conceived in the early twentieth century, the proposal was estimated in the 1920s to cost between $75 million and $100 million and to generate about three billion kilowatt-hours annually.

LocationPassamaquoddy Bay and Cobscook Bay
Core ideaGenerate electricity from the recurring movement of ocean tides
1920s estimate$75–100 million in contemporary project costs
Projected outputAbout three billion kilowatt-hours per year
Rocky shoreline and islands bordering a broad coastal bay
The proposed system depended on the strong tides and complex coastal geography of the Passamaquoddy and Cobscook Bay region.

A cross-border plan

“Quoddy” was envisioned as a system spanning Passamaquoddy Bay in Canada and Cobscook Bay in Washington County. After initial interest, however, the Canadian government withdrew permission when fishermen protested the potential loss of valuable fishing grounds.

The international geography was central to both the proposal’s promise and its difficulty. Engineering works across connected bays required coordination beyond Maine and the federal government, while fishing communities had direct concerns about changes to productive coastal waters.

Depression-era public works

During the Great Depression, the Public Works Administration sought projects that could create employment. Federal reviews nevertheless concluded that the Quoddy proposal was too expensive and could not compete with lower-cost electricity from steam plants.

With Governor Louis J. Brann championing the idea and Franklin Roosevelt in the White House, several million dollars had been allocated by 1935. The Army Corps of Engineers used those funds for preliminary studies and tests. The project’s prospects dimmed again when Congress eliminated funding in 1936.

Historic engineering plans and drafting instruments on a work table
Studies tested the engineering and economic assumptions behind an unusually large coastal energy system.

The unresolved market question

A major problem was the absence of a clear market for the electricity the project might produce. Advocates advanced several schemes for transmitting power across the country, but inconclusive market studies persuaded few decision-makers.

The debate was therefore not only about whether tidal generation was technically possible. It also concerned the cost of moving electricity to customers, competition from other energy sources, and the extent to which public funds should support an uncertain market.

Politics and later revival attempts

Democrats actively supported the project in Maine and incorporated Quoddy planks into party platforms. Republicans initially declined to do so, although Maine senators, representatives, governors, and many state legislators from across the political landscape supported the proposal. Some regarded it as public spending from which Maine deserved to receive a share.

The Democratic platforms of 1934, 1936, 1938, and 1950 illustrate the project’s political persistence. Beginning with its 1950 platform, the Republican Party also supported the idea and continued to do so through the 1970s.

A brief revival effort in the 1960s connected tidal generation with northern Maine river-power proposals, including Dickey-Lincoln. Once more, political and environmental concerns outweighed the tidal project’s prospects. Suggestions that the site instead host a naval base or another military facility produced no substantial development.

Project chronology

From proposal to repeated reconsideration

Quoddy moved through private advocacy, international concerns, federal study, congressional withdrawal, and later attempts to revive the concept.

The concept emerges

A large tidal hydroelectric system is proposed for the interconnected bays.

Scale is estimated

Advocates outline substantial costs and an annual output near three billion kilowatt-hours.

Study, then withdrawal

Federal funds support preliminary work before Congress ends financing.

The idea persists

Revival proposals connect Quoddy with other power projects, but do not advance to construction.

Further research

Selected sources

These archival, historical, and scholarly works document the proposal’s engineering, policy, and political history.

Emery, Roscoe C. Papers, 1900–1970. University of Maine, Raymond H. Fogler Library, Special Collections.

Holmes, Theodore C. A History of the Passamaquoddy Tidal Power Project at Eastport, Maine. Portland, Maine: T. C. Holmes, 1992.

Marvin, George R. The Passamaquoddy Bay Tidal Power Project and the New Deal. Honors paper, Department of History, Bowdoin College, 1972.

Moreau, Raymond. Passamaquoddy Tidal Power: An Analysis. M.A. thesis in political science, University of Maine, 1977.

Smith, Lincoln. “Tidal Power in Maine.” Land Economics, August 1948, pp. 239–252.

FAQ

Understanding the Quoddy proposal

Concise answers to the central questions raised by the project’s history.

What was the Passamaquoddy tidal power project?

It was a proposed hydroelectric system intended to capture energy from the large tides moving through Passamaquoddy Bay and Cobscook Bay.

Was the project ever built?

No. Preliminary studies and tests were conducted, but the complete generating system never received sustained funding or entered construction.

Why did Canada withdraw its permission?

Fishermen objected to the possible loss of valuable fishing grounds, adding a major cross-border obstacle to the proposal.

Why did federal funding end?

Federal officials questioned the project’s cost and competitiveness, while Congress eliminated its funding in 1936.

What economic problem did advocates face?

They could not establish a sufficiently clear market for the projected electricity or a persuasive, economical plan for transmitting it to customers.

Did interest end in the 1930s?

No. Political platforms continued to support the idea, and an attempted revival during the 1960s linked it with other proposed power developments.